We have a LPE 200, that works fine, but after sitting for 5 mins or so, will only allow slow speed drive, and display reads 2.282. Hydraulics function as normal, just speed is reduced. Any thoughts on this? Any info on code 2.282 ?

Thanks a million fellas.
  • Posted 21 Jun 2022 22:09
  • By s_k_
  • joined 25 Jun'18 - 12 messages
  • Ontario, Canada
Komatsu, and Crown, experienced. Let me know what I can help with!
Showing items 1 - 2 of 2 results.
Thanks a million brother! This will help me greatly! SO appreciated! Cheers!
  • Posted 21 Jun 2022 23:53
  • By s_k_
  • joined 25 Jun'18 - 12 messages
  • Ontario, Canada
Komatsu, and Crown, experienced. Let me know what I can help with!
2:282 Platform sensor activated
The platform sensor has been
activated for more than 5
minutes without any truck activity.
Truck behaviour
Creep speed
* Platform loaded
* Constantly high signal
from B119
* Constantly high signal at
inputs T1:101
1) Handling error - no action.
2) Check the sensor signal
Check that the distance
between the sensor and
the opposite part is correct.
Check that there is no
dirt or foreign objects on
the sensor
Inspect cabling.
Measure the signals
from the sensor with a
volt meter and verify using TruckCom or the
built-in test that the signal is correct
3) Check the signal to the
unit
Compare the signals
from the sensor with the
input signal (use a volt
meter and verify using
TruckCom or the built-in
test that the signals are
the same)
Check the pins on the
unit and in the connector
Replace the unit if you
cannot get it to work
properly
  • Posted 21 Jun 2022 23:51
  • By andrew_k
  • joined 17 Mar'07 - 337 messages
  • England, United Kingdom

Post your Reply

Forkliftaction accepts no responsibility for forum content and requires forum participants to adhere to our rules of conduct. Click here for more information.

If you are having trouble using the Discussion Forums, please contact us for help.

Global Industry News
edition #1258 - 27 November 2025
In this week’s Forkliftaction News , we report on Hyster-Yale laying off staff in the US amid what it describes as “challenging market conditions”... Continue reading
Editorial calendar - planned features
CONSTRUCTION FORKLIFTS
HANDLING GOODS IN THE COLD
LOADING/UNLOADING FREIGHT
BROWNFIELD AUTOMATION
FORKLIFT ATTACHMENTS
BATTERY AFFORDABILITY AND LIFETIME
FORKLIFT SAFETY
Global Industry News
edition #1258 - 27 November 2025
In this week’s Forkliftaction News , we report on Hyster-Yale laying off staff in the US amid what it describes as “challenging market conditions”... Continue reading
Upcoming industry events …
December 4–7, 2025 - Goyang, Korea, Republic Of
March 10-12, 2026 - Hong Kong, Hong Kong
June 30-July 2, 2026 - Birmingham, United Kingdom
Fact of the week
According to studies published in the English Journal of Medicine, the impact of daylight savings is revealed by a 24% increase in heart attacks on the Monday following the spring shift forward. When clocks move back in autumn, heart attacks drop by about 21%, suggesting that loss of sleep is an important driver.
Global Industry News
edition #1258 - 27 November 2025
In this week’s Forkliftaction News , we report on Hyster-Yale laying off staff in the US amid what it describes as “challenging market conditions”... Continue reading
Fact of the week
According to studies published in the English Journal of Medicine, the impact of daylight savings is revealed by a 24% increase in heart attacks on the Monday following the spring shift forward. When clocks move back in autumn, heart attacks drop by about 21%, suggesting that loss of sleep is an important driver.